During the week of October 19, the Military Ridge State Trail will be closed in three places around Verona simultaneously. A bridge replacement downtown has closed the stretch between Lincoln Street and South Franklin Street. Epic's Hyper Drive road project has closed a 0.75-mile segment near Epic Lane. West of town, the Wisconsin DNR has scheduled bridge maintenance that closes 1.5 miles between Hwy. J and Hwy. PD from October 19 to 23.
Each closure has its own cause and its own agency. The downtown one starts something longer. That bridge is the first of three bridge replacements the City of Verona has to finish before it can pave the trail from Old CTH PB to just west of Wildcat Way. The downtown detour you ride this fall is the first stage of that work.
The three closures at a glance
| Closure | Location | Dates | Detour |
|---|---|---|---|
| City bridge replacement | Between Lincoln St and S Franklin St, downtown | Sept 14 to approx. Nov 13, 2026 | Walkers: Lincoln and S Franklin to W Verona Ave. Cyclists: Lincoln and S Franklin to Schweitzer Dr |
| Hyper Drive construction | 0.75 miles near Epic Lane | June 12, 2026 to Sept 30, 2027 | Marked route along Epic Lane |
| DNR bridge maintenance | 1.5 miles from Hwy. J to Hwy. PD, west of Verona | Week of Oct 19 to 23, 2026 | None posted; DNR asks users to stay out of closed areas |
The downtown closure dates come from two places. The city's September 9 notice says the section stays closed "through mid-November." The DNR's property notice, updated September 22, gives a firmer end date of approximately November 13. The detour splits by mode. Walkers use Lincoln Street and South Franklin Street to reach West Verona Avenue, north of the trail. Cyclists use the same two cross streets to reach Schweitzer Drive, south of the trail.
The Hyper Drive closure will last much longer. Epic is building a road that connects Epic Lane to Hwy. 18/151 and County G and crosses over the trail. The city says the Epic Lane detour runs until September 30, 2027, and that the trail section will open whenever construction allows. The trail is also scheduled to open for snowmobiles from December 2026 through February 2027.
Why the downtown bridge comes first
The City of Verona announced the project in a March 2, 2026 letter to residents. It said the DNR had authorized the city to work on the trail, that three existing bridges would be replaced, and that "after the bridges are installed, the trail will be paved." The bridges have to be finished before any asphalt goes down, so this fall's closure starts the schedule.
The city also gave its reason for the project in that letter:
"The purpose of this project is to provide year-round accessibility for cyclists, runners, walkers, and individuals using mobility devices, improving safety and usability for all trail users."
Today's surface explains why the city says "year-round." Madison Bikes noted in March that the paved trail ends on Verona's east side and that the route west of there is crushed limestone. The project map lists the new section as 9,300 feet long and 10 feet wide. Madison Bikes described it as carrying the east-side pavement west to Verona Area High School. Once it's done, the paved trail will run from the east side of town past the high school.
The rest of the schedule, in order
The city's September notice and its May progress report lay out the remaining steps:
- Now through about November 13, 2026: replace the bridge just west of Lincoln Street.
- November 2026: hold a public information meeting on the paving project. The city has promised it but hasn't set a date, time, or location yet.
- Early spring through July 2027: replace the bridge east of Wildcat Way and the bridge west of Old PB.
- Summer 2027: pave the trail. A May 2026 city progress record says the goal is to finish paving by fall 2027.
The bridge work has a confirmed funding source. The city reports a $550,000 DNR grant for the bridge project. The documents available so far don't say how the paving itself will be paid for. That's a reasonable question to bring to the November meeting.
The DNR's Military Ridge State Trail page says a state trail pass is required for bicycling and in-line skating, and none of the city's project documents mention an exemption.
The city held an earlier public meeting on March 18, 2026, at the Verona Senior Center, 108 Paoli Street. If you missed it, the November meeting is your next chance to see the design and closure plans in person. Until a date is posted, Verona Public Works takes questions at 608-845-6695.
What the Hyper Drive closure adds near Epic
The Hyper Drive closure isn't part of the city's paving project, but it is building trail improvements of its own. Along with the road, Epic is restoring nearly 5,600 linear feet of the Sugar River, turning a channelized ditch back into a natural, winding stream. It is also restoring more than 6 acres of wetlands and 3.5 acres of upland in the valley. The project will add a shared-use path connecting to the Military Ridge State Trail, a public access point on the Sugar River for kayakers and anglers, and a small parking area.
The project hasn't been free of controversy. In May 2024, WMTV reported that some residents worried a proposed Epic bridge would affect wetlands and wildlife. At that point the DNR was still reviewing the permit application. Construction is now underway, and the city's June 2026 notice lists the City of Verona, Town of Verona, Dane County, the DNR, the U.S. Army Corps of Engineers, and the U.S. Fish and Wildlife Service as partners that shaped the project or oversee it.
So by fall 2027, the trail through Verona should be paved from the east side to the high school, and there should be a new river access and path connection near Epic. Between now and then, expect closures to keep moving along the trail.
Trailheads and stops that still work this fall
With the downtown bridge section closed, it helps to plan around the trailheads and stops on either side of it.
- Hometown Junction Park, 101 W Railroad Street. It sits right on the Military Ridge Trail downtown and has off-street parking, restrooms, a drinking fountain, and a picnic shelter. The Verona Downtown Farmers Market meets here on Wednesdays through October 14.
- Verona Park & Ride, near County Highway PB and Verona Avenue. The Friends of the Military Ridge Trail list it as a trailhead with parking and an information kiosk. It's on the eastern end of town, near Old PB, where the paving section will start.
- Alice Good Coffee, 300 South Main Street. A downtown coffee stop a short walk from Hometown Junction.
The walking detour uses West Verona Avenue, which passes a few other October stops. Ian's Pizza is open at 303 W. Verona Ave., next to Century School Park. It serves pizza by the slice or the pie, Calliope Ice Cream, draft beer, cocktails, and slushies. On Saturday, October 10, Century School Park at 309 W. Verona Ave. hosts the second annual Puppets in the House festival. It's free and runs from 2 to 8 p.m., with puppet performances, an art market, food trucks, and a lantern puppet parade.
A few more dates this month:
- Lake Louie Brewing Harvest Fest, Saturday, October 10, from noon to 5 p.m. at 1079 American Way, with pumpkins, produce, live music, and beer.
- Haunted Hike, Friday, October 30, from 5 to 8:30 p.m. It starts at the Fireman's Park path entrance on South Main Street, offers separate time slots for less-scary and scarier routes, and costs $2 cash.
For long rides west, check the calendar before you go. The DNR's Hwy. J to Hwy. PD closure runs during the week of October 19 to 23. The downtown detour is in place until mid-November, and the Epic Lane detour stays up through September 2027. The city's Military Ridge State Trail Paving Project page at veronawi.gov is where status updates will be posted.
Construction on trails, roads, and bridges changes how a neighborhood feels day to day, and buyers ask about it. At 47 Bricks Realty, we track projects like the Military Ridge paving so Verona homeowners can talk about them with real dates. If you're thinking about how 2027's paved trail could fit into your home's story, schedule a no-obligation consultation and we'll go through it with you.